Instantis 9.0 - be able to reschedule and update basic even to change basic Dates and Efforts to not selected activities

In change system profile/role permissions for the project it, there is an option to allow a role to change the planned Dates and Efforts for activities.

If that is not selected, a user cannot change the benchmark for Dates of the activity fields.

However, it seems that the same user can perform that function reschedule and pick update planned and Baseline.  This changes the basic dates, even if the option is not selected.

This work is designed?

It seems that you should open an SR for this one.  I know that you can restrict who can update the base line, but I thought that this has also limited recalculation and updated in this way.

Tags: Oracle Applications

Similar Questions

Maybe you are looking for