Variables in SubVIs reset on each call to MCB2400 in LV2009 ARM embedded

Hello

I have a problem with variables in SubVIs. If I put them on my MCB2400 (ARM) they reset at each call. So it s impossible to build a counter in a Subvi. If I run the same VI on my PC, everything works fine. Just on the ARM it doesn´t work more.

In my example (see attachment) to build two counters. A hat of the Variable to increment in the mainVI and the other in the Sub - VI. And that, in the mainVI the other not work (on the MCB2400). But if I run the same on the PC, both work without any problem.

Anyone has an idea where is the mistake of m or is this a bug in the LV2009 ARM embedded?

Bye & thanks

Amin

This isn't a bug.
When it comes to read the local variable program gets a value of the indicator that is in your PC, not on the target. Control/indicators are not updated continuously, but with the specified period in "Configure the target" of dialogue. In your application you do not give a chance for the indicator update until the next iteration.
However, it is not recommended to use local variables. You can use something like this:

As an alternative, you can use 1 iteration loops store this local in a shift register.

Tags: NI Products

Similar Questions

  • After update, tools of default reset for each new application launch

    Hi, my recently updated team to update to the latest version of CC and we view every time that we launch, our pot of paint guard reset to the default value in the gradient tool, our pencil tool restores brush, etc. It's very frustrating because we use the program all day every day. Sometimes I don't remember close Photoshop at all and it seems that the tools to reset? Y at - it an option to stop this, I'm not.

    Hi 812 b,.

    It is a known issue with version CC2015.1 and the engineering team is currently working on this topic.

    The workaround is to disable 'show the initial working space' in the Photoshop preferences > General.

    Reference article: Photoshop CC 2015.1: reset with each launch tools

  • reentrant VI copies the entire structure VI (of Subvi) when it is called?

    Hello world

    I would ask each of you about the reentrant VI.

    I have a VI (Thread.vi), which is set to reentrant (Preallocated clone reentrante execution) that is called from the main vi using the method run a VI. Reference of vi is open with all of the option 0 x 8.

    When I call the Thread.vi, the original vi clone is created.

    My question is, when the clone of the first level vi (Thread.vi) is created, all the Subvi contains the Thread.vi is also the Subvi originally clones?

    Going to queue named in the Thread.vi when it is called by using the control property value node and using this queue within the Thread.vi (in sub - VI) to control the Thread.vi.

    My problem is that when two clones are created, I can run, stop, and close the two together. But when I want to close the second clone, the Dequeue function reference to queue the first clone. I do not understand what the queue has been obtained with the name in the main vi and spent in the clone of Thread.vi. When I want to close the first clone, it works as it has reference to the appropriate queue.

    I thought that LabVIEW creates entire hierarchy of the Subvi the reentrant VI so when it is called.

    Thank you for your answers and help.

    Tukan

    I'm using LabVIEW 2014 32 b, Windows 7

    You use named queues, so unless you call your clones several times (rather than, say, calling a clone and get running code in a loop for a "long time"), I would recommend not worrying to pass a reference queue for the Clone, but rather the name of the queue.  Get the Clone of its own queue - if the hand is already done, get queue of the Clone will not allocate a new queue, but returns the reference to the queue already created.

    Screws that are used by the Clones can be "specific clone" (if they are, themselves, marked as Reentrant) or 'universal' and shared by all of the Clones.  There is really nothing wrong with that, as long as you realize that while A Clone uses void-VI X, Clone B will be "blocked" when it tries to use the Subvi, if you want to run in a mode of the Subvi '-and-out ", without blocking.  In particular, not to put any function, for example a Dequeue, who must wait in a common Subvi.

    Bob (who has learned this "rule" with the sad experience) Schor

  • Create a Windows 7 user profile which resets after each reboot.

    I want to configure a limited in Windows 7 user profile that performs the following steps after EACH restart or disconnection:

    • Reset the background / theme
    • Reset the desktop icons / shortcuts
    • Network mapped reset drives
    • Reset saved passwords
    • Delete the data stored since the last session
    • Remove newly installed applications / block the installation of the application
    • Reset the print queue to empty - if it was not already
    • Reset the default printer
    • Reset the homepage Internet Explore & settings
    • Reset the screen resolution

    The idea is to create a profile for workstations in an office of the admin who works a bit like an internet café. They have a couple of shared workstations, a network printer, and they store the data on a file server and work on a local application server.

    The current problem is that they constantly record their passwords, remove network drives and change the General configuration of work stations (by chance), which makes it difficult for other users to work - that they do not recognize the look & feel and now don't know where to do what.

    I want to create a 'shared' user profile where they can log on, and everything looks familiar. All settings are saved as defaults and no matter what you do, as soon as you log out or restart, the parameters of return by default.

    I would appreciate help.

    Here are a few options:

    • Windows steady state (http://www.microsoft.com/windows/products/winfamily/sharedaccess/default.mspx). The product is supported for Windows XP and Vista, but maybe it works for Windows 7 too. Or maybe there is an equivalent Windows 7 somewhere.
    • Create a scheduled task that runs at boot time. You must run this command:
      Robocopy c:\Users\UserName.bak c:\Users\UserName/s / r: 1 w:1 /MIR /IS /IT /np 1 > c:\Windows\temp\restore.log 2 > & 1
      Note this:
      -Before starting, you must use the robocopy command in reverse so that it fills the C:\Users\UserName.bak folder.
      -The task must be run under the system account.
      -The task will run with the highest privileges.
      -Use during the testing of the installation log file. Subsequently you can pass you.
      -L' tool does not reset passwords. You must create a policy that prevents users from changing the password.
  • The synchronized application: creation of menu items for each call to makeMenu SQLite?

    A matter of design, which is a good implementation of the following?

    My requirements are:

    1. Have a different menu for each screen.
    2. The battery of the screen will be high both a single screen.
    3. To switch screens, the user must use the menu.

    I created the menu for each screen by the following:

    protected void makeMenu(Menu menu, int instance) {
    super.makeMenu(menu, instance);
    Database db = null;
    try {
    
      db = ResourceManager.getConnection(true);
      mCoffeeDao = new FlavshellDao();
      mTabDao = new FlavmDao();
    
      if (instance == Menu.INSTANCE_CONTEXT) {
          Bitmap logoWbg = Bitmap.getBitmapResource(resource
                  .getString(ScoreCenterResource.logo));
          Image image = ImageFactory.createImage(logoWbg);
    
          gMenu.setIcon(image);
          nMenu.setIcon(image);
          aMenu.setIcon(image);
          shMenu.setIcon(image);
          avMenu.setIcon(image);
          logoMenu.setIcon(image);
    
          menu.add(gMenu);
          menu.add(nMenu);
          menu.add(aMenu);
          menu.add(shMenu);
          menu.add(avMenu);
          menu.add(logoMenu);
      }
    
      if (instance == Menu.INSTANCE_DEFAULT) {
          menu.add(logMenu);
          menu.add(exitMenu);
    
          shell = mCoffeeDao.findAll();
    
          for (int i = 0; i < shell.length; i++) {
              Flavshell m = shell[i];
              /**
               * Ordering parameter, lower values are placed closer to the
               * top of the menu screen.
               */
              item = new FlavMenuItem(m.getPk(), m.getFlavortitle(),
                      200 + i);
              menu.add(item);
          }
    
          String[] params = {
              Integer.toString(this.mCoffeePk)
          };
          Flavm[] m = mTabDao.findByDynamicWhere("FLAVOR = ?",
                  params);
    
          if (m.length > 0) {
              for (int j = 0; j < m.length; j++) {
                  if (m[j] != null) {
                      Flavm specificMenu = m[j];
                      item = new FlavMenuItem(specificMenu.getPk(),
                              specificMenu.getTitle(), 100 + j);
                      menu.add(item);
                  }
              }
    
              menu.add(MenuItem.separator(105));
          }
      }
    
    } catch (FlavshellDaoException e) {
      Logger.logEventError(e.getMessage());
    
    } catch (FlavmDaoException e) {
      Logger.logEventError(e.getMessage());
    
    } finally {
      try {
          db.close();
      } catch (DatabaseException e) {
          Logger.logEventError("Menu Database error: " + e);
      }
    }
    

    I created a database with a single link object read in the following text:

    public synchronized static final Database getConnection(
        final boolean readOnly) {
    Database db = null;
    try {
        URI userFileURL = URI.create(System
                .getProperty("fileconn.dir.memorycard")
                + resource.getString(CoffeeHouseResource.db_path)
                + resource.getString(CoffeeHouseResource.db_name));
    
        db = DatabaseFactory.open(userFileURL, readOnly);
    
    } catch (MalformedURIException e) {
        Logger.logError("Get connection: URI: " + e.getMessage());
    } catch (ControlledAccessException e) {
        Logger.logError("Get connection: Controlled Access: "
                + e.getMessage());
    } catch (DatabasePathException e) {
        Logger.logError("Get connection: Database Path: "
                + e.getMessage());
    } catch (DatabaseIOException e) {
        Logger.logError("Get connection: Database IO: "
                + e.getMessage());
    } catch (Exception e) {
        Logger.logError(e.getMessage());
    }
    return db;
    }
    

    My question is,

    • If the user to call the menu as happening in any other activity database (SQLite), making the synchronized method will prevent database locks?
    • Should I design my makeMenu got a call from the database at all? It seems to me that all this works, this could potentially cause a lot of traffic on the SQLite database?
    • I thought to move the menu to a vector and storing the menu in storage Runtime, but I read that the Runtime Storage has the memory leak issues?

    Your basic design principles seem well - I have a number of applications that actually have "tabs" screens, so clicking on a tab or using the menu swaps from one screen to the other.  You can just push the new screen and pop, that. In fact, here's a menu from a screen, that I am currently working:

    _StatsMenu MenuItem = new MenuItem ("Stats", 110, 10) {}
    public void run() {}
    UiApplication.getUiApplication () .pushScreen (new StatsScreen (System.currentTimeMillis (), 0));
    UiApplication.getUiApplication () .popScreen (BaseScreenWithToolBar.this);
    }
    };

    While I haven't looked in detail, but your code dangerous look.

    I've never tested, but I suspect makeMenu is called using the EventThread.  Doing things like database connections in this method will cause you problems.  Do not.  If you need to query the database, do so before makeMenu is called.  Starts a separate Thread and set the appropriate menus if this Thread is not finished.  or block the user interface, until he made.

    In addition, I wouldn't do it in makeMenu:

    Bitmap logoWbg = Bitmap.getBitmapResource (resource
    .getString (ScoreCenterResource.logo));
    Image image = ImageFactory.createImage (logoWbg);

    You can do it once to the creation of the screen, or better yet, once at startup and save it in a shared domain.

    If you do not want to create a dynamic menu, then use the normal persistent store - or check out the details for the database once at startup and use them after that RAM.

    And avoid lifting heavy objects in makeMenu.

    I hope this helps.

  • Each call cause VerticalFieldManager.add (child) to "available" to already added childs method call.

    Is it possible:
    -ban VerticalFieldManager child call "sublayout" at the beginning;
    -Add multiple items;
    -push the VerticalFieldManager to call "sublayout" of all children.

    Here are two possibilities:

    1. Call UiEngine.suspendPainting (true) before adding the items, then call UiEngine.suspendPainting (false) (and perhaps invalidate()) later. Note that UiApplication implements UiEngine. I'm not sure that it works; It can only block calls to object, but it can also block calls to sublayout.
    2. Remove the VerticalFieldManager of his manager (or screen) before adding items. It may be that a Manager will not call sublayout if they belong to a screen.

    If none of these work, you can create a subclass VerticalFieldManager, add an indicator variable that indicates whether sublayout should move forward and then override sublayout in order to respect the flag. You can force a sublayout at the end by calling invalidate().

  • the initialization of a variable in a bpel workflow to call another web service

    Hello

    I'm fairly new development bpel. I don't have a early created myself but unfortunately, I only got to work on existing projects from now on. I am wanting to add an invocation of another web service to an existing bpel service. I added the wsdl for .bpel and composite.xml files info, and I can see the operations, so my plan is to see the service properly, and I created the necessary links.

    I just need to initialize the variables that I'm passing on this web service. Basically need to invoke the web service passing in xml format that would go into these elements:

    < ns1:dataRequest >
    < ns1:appName > < / ns1:appName >
    < ns1:progName > < / ns1:progName >
    < ns1:valueUsed > < / ns1:valueUsed >
    < ns1:setting > < / ns1:setting >
    < / ns1:dataRequest >

    Can someone just point me in the right direction on this. I think I need to create a new .wsdl file that I've read so far, but I have a lot of time looking for this problem - it is low on my priorities. So I thought that it might accelerate things to go ahead and ask here before I dive into it later.

    Thank you

    Hello

    As far as I get your situation is you want to call a web service from BPEL process existing. Here are the steps that you can follow.

    (1) create a partner link in the BPEL process that calls the external Web service.
    (2) create an activiyt to invoke in BPEL process that invokes the foregoing created partner link
    (3) create an Assign activity that initializes the variable which is an entry to invoke activity.

    Let me know if you have confusion with this approach.

    Thank you
    AJ

  • Is there a way to RESET a PDF called Reader9?

    Is there a way to RESET all form fields in a file called PDF? I want to clear all form fields in the PDF document entitled "File Client" because open in the example below.

    var otherDoc = app.openDoc("..) ("/ Configuration/file customer", this);

    Try this:

    otherDoc.resetForm ();

  • Why the Mac calendar window height reset with each launch?

    The calendar application has recently begun to reset the height of the initial window every time I run the application there. I put the location and size of my windows in the application in the manner that works best for me. Apps remind this location and size so that I don't have to go through the process over and over again. Now the calendar app remembers the location and width of the window, but always resets the height at a little more than half of the height of the screen. I have to drag the lower limit of the window to the bottom of the screen every time that I run this app.

    I use Mac OS X 10.11.2 and calendar 8.0 (2092.2) at the moment.

    I have the same problem.

    From what I've heard, many others also have.

    For me, everything began with the introduction of OS X El Capitan.

  • Why this Subvi takes longer each time I run it?

    I'm running this Subvi inside a loop, with say 2000 iterations. As the iterations increase, I notice that the time increasing, starting around 15ms when I = 0 and move upward constantly until it is around 100 ms to i = 2000.

    Do us admit that there is a method to my madness and not get bogged down in why I want this turning on and off 2,000 times. I have a similar Subvi in the same Hoop, which made a few signals in input/output tasks, which shows the same problem on a large scale. I notice a memory leak when I look at the Windows Task Manager as well.

    I guess the task of tension is created every time that's the problem, and I can certainly go to move before the loop. But I do not understand where va-the lost time. It has to do with how Labview stores/access tasks maybe?

    My guess?  You are creating a new task every time but without closing the if you find yourself using all of the resources on your computer.

  • Two applications of CVI each calling another version of TestStand

    We have a Test Manager software written in LabWindows CVI.

    A version of the Test Manager wrote in a version more old of the CVI and calls TestStand 3.x.

    A newer version was written in CVI 7.x and also calls TestStand 3.x.

    The latest version of the Test Manager is written in the most recent CVI and the last TestStand.

    We want to install and run the old versions and the new versions on the same PC.

    Will this work?  How the old (and new) Test Manager will select the appropriate version of TestStand?

    For example, we want to execute CVI 7.x and later with TestStand 3.x and with the latest version of TestStand.

    I read the posts earlier to have several deployments of TestStand (or versions) on the same PC.  This case is not quite the same, given that the application calls TestStand and not the opposite.

    Thank you

    RayR

    I don't know which posts, you reference, but they should apply to your situation. The editor interfaces and operator of sequence are not TestStand. They both call the TestStand engine. Because you can only have a single engine was active at a time, you will need to have your high-level program go to the correct. There are a few files of commands here that should help you. Of course, you can run your manager different test programs at the same time.

  • Stop button does not reset after each program start

    Newbie here, so when I start the program with the arrow of departure or, my Start button is always in the right position, but the stop button is not. How do reset you the default user as the stop button control.

    Lol it doesn't have the same effect.  They are completely different actions.  If they were the same, then NEITHER would never have created the other.  I've never seen a practical use for 'Up to this that freed'.  Read the help files on the mechanical actions to see the difference.  There is a real difference, delicate and subtle.  But there is a difference.

    If you clean the Boolean logic and put the start in case structure button.  It works very well.  See attachment.

  • Speaker blackBerry Smartphones answers each call

    Whenever I get a call and press the talk button on my phone's speakerphone for 5 seconds and then it returns to normal. Is there something I can do to fix this? I had this phone for several months and it happened more than a day now.

    Hi and welcome to the forums!

    No data will be lost when you do the following: remove the battery while the device is activated.

    Remplacer replace after one minute, let the device reboot 1-3 minutes, see if the problem is corrected.

    Thank you

    Don't forget to adjust your thread. Put the check mark in the green box containing your answer! Thank you

  • Reset time: each reboot the laptop, the exact time is displayed. Towards the end of the reboot process, time passes before 2 or 3 hours.

    The date still remains correct. In the summer, I recall is that time jumps before 2 hours; in the winter of 3 hours. I used this laptop in Arizona, which does not use DST. A clue?

    Hi Whitewind.If you left click on the time at the bottom right, it will bring up a menu. Select change the date and time. Click on it then go to the time of the internet on the tabs, then click on change settings. Uncheck synchronize with internet time. Set the right time and it should remain. It can be when windows has been implemented the incorrect time zone has been selected.

  • BIND THE VARIABLE INSIDE A LOOP

    Hello
    I have question about the sort of the values using Plsql... My requirement is to get values of N with the user and sorting in ascending or descending order. I tried the following query

    DECLARE
    Is of type TABLE numsort
    NUMBER
    INDEX OF DIRECTORY;
    v_num numsort;
    number of v_total;
    number of v_no;
    BEGIN
    -get the number of values to sort
    v_total: =: TotalNum;
    dbms_output.put_line (v_total);
    because me in 1.v_total
    LOOP
    v_no: =: none; -Read the values
    v_num (i): = v_no;
    dbms_output.put_line (v_num (i): 10;)
    END LOOP;
    END;

    its code is not complete... sound to read the value in the table... Read itself does not

    The problem is that the connection variable is not reset with each iteration. I am using Toad and he asked me to pass all the variable binding both... But I want to read the values in the table with each iteration. Is it possible in PLSQL... or is there another way to do this...

    hope you are clear with the requirement... If any infomartion extra need please come bk...

    Waiting for your replay

    Thanks and greetings
    Rognard

    Maybe like this?

    SQL> create or replace procedure test_proc (p_input varchar2, p_separator varchar2) is
      2  v_input varchar2(32767):= p_input||p_separator;
      3  begin
      4  if p_input is not null then
      5  while instr(v_input,p_separator) > 0 loop
      6      dbms_output.put_line(substr(v_input,1,instr(v_input,p_separator)-1));
      7      v_input:=substr(v_input,instr(v_input,p_separator)+1);
      8  end loop;
      9  end if;
     10  end;
     11  /
    
    Procedure created.
    
    SQL> exec test_proc('10, 4, 6, 3',',')
    10
    4
    6
    3
    
    PL/SQL procedure successfully completed.
    
    SQL> exec test_proc('',',')
    
    PL/SQL procedure successfully completed.
    
    SQL>
    

    Nicolas.

Maybe you are looking for