Approved cost budget & approved revenue budget

Dear Dina,

In which case we can decide if the costs and budget revenues is necessary for an organization? or only analytical budget only revenue budget or cost and income have together?

kindly help me to understand... Thanks in advance much n...

Hello

When the method of income generation is the COST (increased from percent), the project must have approved the costs and revenues of Budgets.
In case you want to make the value assessment and measurement of the results of the progress of the project you must cost budget.
Otherwise, there is no limit in the system.

Seizure of budgets and comparing actuals to budgets are essential activities of project management and are recommended as a professional practice by most project professionals.

Dina

Tags: Oracle Applications

Similar Questions

  • Approved revenue budget

    Without any manual intervention oracle project based on some calculation (formula) divide the cost to the budget of income?

    Is it possible to oracle projects? If any 1 know pls help me...

    Thank you n advance...

    Hello

    Oracle project does not divide the cost.
    If you want to generate approved revenue budget based on planned amounts, then you need to install a financial plan for the budget of income and assign the rate schedule for billing rates.

    Dina

  • Number of management and cost budget version

    Dear Dina,

    When to go for management of the issue and when to go for a new version of budget cost...

    Pleaseeeeeeeeeeee help me understand...

    Thanks in advance much n...

    Hello

    Management of the issue is not linked to financial amounts. Usually, the project team can raise issues they need to be discussed and decided during the execution of the project.

    You can enter updated budgetary cost and submit for approval, if there is a change with the exception of the complete estimate cost or scope of the project.

    In some organizations, they manage the change project in a very strict discipline. They raise a change request and then submit it for approval and an order to change approved. A rider can be linked to financial implications, cost, income, or both. In this case, there is a form to apply stopped financial effect of change as update of the financial plan.

    Dina

  • Revenue Budget approved by copy of values funding of

    Hello gurus,

    In the implementation of our projects, we expect to create the approved Revenue Budget

    exactly the same as what is recorded as funding without planning resources.

    Is it possible to automatically copy the amounts of funding in the Budget of income approved using standard functions?

    If there is a way, are there requirements for the use of this function?

    We use project management to create the Budget approved recipes are on R12.1.3 environment.

    (We need the revenue for calculating % completion).

    Kind regards

    Satoko

    Hello

    You will need to use the API to automatically create budgets. Current feature allows you to create funds and be automatically computing base (no budget revenue is created in this case) or manually create an economic version that allows you to extend funding through tasks up to the amount of the funds allocated.

    If you have formalized procedures to allocate budgets of income, you can call procedures API to automate the task.

    PA_BUDGET_PUB. CREATE_DRAFT_BUDGET and PA_BUDGET_PUB. BASELINE_BUDGET are the procedures you should look at.

    Thank you

    Gene

  • Why the customer financing is required at the level of the approved Budget income reference?

    Hi guru of the project


    Why customer financing is required at the level of reference approved Revenue Budget? Is possible on the revenue budget approved with funding of reference customer? can we use other budgets as budget revenue planned instead to use the approved revenue budget.

    your help is much appreciated. AM starting in project accounting...

    Thanks and greetings
    Shameer PIT

    Hello

    Go to Setup > projects > project types
    Find the type of your draft contract and look the billing information tab. There is a checkbox for funding without base Budget. This option to relieve the linkage that see you, where the funding should match the approved revenue budget.

    In addition, you must configure a different name for the type of budget. Do not use the reserved name approved Budget receipts. You can use any other name for this type of budget. Then you are free to enter and baseline that budget without limitations.

    Note If you revenue recognition method is COST, Oracle hope you approved Revenue Budget equal to allocated funding. The billing COST-COST extension uses this type of budget in the formula. If necessary, update the settings of the extension of billing of COSTS-COST to use your selected budget type.

    Dina

  • Automatic generation of revenue budget based on the funding agreement

    Dear Dina,

    I use project management to create approved budget revenue plan... kindly advice me how can I self-generating revenue budget based on my allocation of funds agreement?

    I am allocating funding based on the albums project task... If a project has received more than 15 albums tasks... 15 lines must be defined in the funding agreement. his activity of reproduction must be done creating revenue... kindly help me to avoid repetition...

    Thanks in advance much n...

    Hello

    Go to configuration > projects > Project Types
    Set up a type of contract class.
    On the Invoicing tab, check the box: base without Budget funding.

    The system will now create automatic revenue planned for the project, after you allocate to base funding for the agreement and you the funding for the project.

    With the help of this feature you don't need to manually enter an approved Revenue Budget.

    Dina

  • The fiscal integration & budget control

    Hello

    In JSP project management pages, I created "approved cost & revenue Budgets."

    and create subsequently 'estimated cost Budget' in the form of calculation of the costs of project Budgets.

    I was able to integrate the budget expected to GL through bottom up integration cost.

    I need to confirm someone who has used the same solution as if my activities of accounting & Billing (amount invested) will remain unchanged by the "forecast of the cost"(créé sous forme de calcul deles de coûts dele de projet) budget amounts and totally guided by "approved cost budget amounts" that I create in JSP in PM. ""

    Very Urgent.
    Everyone was invited to share views.

    Kind regards
    ADI

    Hello

    Integration of the budget and budgetary control use the type of budget (forecast...) you entered on the budget form.
    Approved budgets that you entered on the pages of project management are not affected by the people. Project management reports do not recognize the budgets of basic shapes.

    Dina

  • Project cost transfer is not updated in average cost?

    Hi Experts,
    I made a transfer project and then performed a cost of updating the item that received the medium material.
    When I start the transfer of the cost of the project, the project management module shows that the project of transfer transactions in control > project Transactions Import > review of Transactions.

    It does not show the average cost update operation?

    Why?

    Hello

    Your question is going back to the basis of the accounting of the project.
    Oracle's design for installation where GL display option is set to project, is based on the concept that most of the costs for a project will be cost of sales you generate income based on the WORK or COST.
    In this concept there is no need to take account of the value of items stored in the warehouse (in stock), as the cost of purchase or collect these points is already adapted to receipts over the same period cost incurred.
    Looking at that, the update of the average cost will affect only the cost of transfer of future project, but has no effect on the cost of the current project.

    We use the same GL display option, but they have cases where it must take into account the value of the inventory. This is the case where a project incurred costs but we still do not recognize the revenue over the same period. We have a solution that send accountants for the value of the inventory at the end of the period, but we do not take into account detailed transactions that affected this inventory as updated cost, damaged objects, obsolete items, etc. Our solution uses billing extensions in projects, similar to the model delivered by Oracle - allocation of the costs of the revenue base. You can see this model in the project guide, billing.

    Dina

  • We can add a button to the BP to approve Budget so that it can read all the charges in question cost journal line and auto fill on the grid.

    Hi all

    We can add a button to the BP to approve Budget so that it can read all the charges in question cost journal line and auto fill on the grid.

    Let's say I have a cost with 5 code cost journal

    Code 1 price

    2 cost code

    Code 3 cost

    Code 4 cost

    Code 5 cost

    BP budget approval, after that I click on New, can I add a button to the tab the line items so that when I click on this button, it reads all codes of cost in the cost journal and auto fill on the grid?

    You can create a new 'model' BP for this purpose. Line item type. Then add a line manually with a cost on each code. Then you can use the copy in your BP BA record consolidate the function to copy the line items to the new folder of BP (including all cost codes) into your folder of BA. That is to set up a model record once with all cost codes and then copy consolidate billing it to all lines new record of BA. would this work?

  • Task-based income splitting

    Hi all

    We have two billable tasks of top on projects, and we are in the order of distribution of the costs-cost of revenue based on cost based on the task, is there a way to generate separate revenue two cost-based accounting lines accumulated on the job in two. (We use a type of work on each task as an identifier to generate revenue for example)

    Concerning
    DR

    Hello

    You could fund the project at the level of the top of the task page.
    The revenue budget approved need to have budget lines by top spot.
    The approved cost budget should have budget lines at the top spot.

    Assuming what install you, you can create an extension of billing that calculates what percentage of each task at the top of the page and multiply it by budget revenues (referenced Fund) the task at the top of the page. This will give you receipts accumulate each task at the top of the page. The extension then creates a revenue event separate for each task that is greater than the cumulative amount income less the prior total income if the task at the top of the page.

    Dina

  • Large screen rear-PSI project charge only in form

    Dear Dina,

    I had taken the implementation on design approved cost budget and revenue approved through Web pages... The budget values are non-reflecting screen PSI?

    how he's enduser budgets create? So happy that oracle introduced Web pages and other side she has unigue PSI it have 1 side is totally frustrated. Preparation of the budget form based does not support too the microsoft integration? !!!

    What is the solution for this?

    Hello

    Financial plans entered in web pages are only displayed using html pages. You can report it by using the page project performance, which is similar to the PSI view reports.

    If you need maintain budgets different types, you might have part of them on the web and other forms.

    If you need to see the amounts of financial plan in PSI, you might consider customizing the system, when the financial plan is referenced, call you the API to copy yhe amounts in the budget lines related to the structure of forms

    Dina

  • Project invoicing - Invocing on the percentage of work complete

    Hello

    Could someone explain please on the process of billing for this criterion to bring up the Bill.

    I'm working on the project of implementation, our Client follows a process of billing their clients at three different stages, they are as follows:

    a. on the 30% work complete / advanced - need to raise a first Bill
    (b) 60% of work completed/WindowFX - need to raise a second invoice
    c. 100% of work completed/WindowFX - must raise a final bill and having to generate income to 100% work complete.

    Our customers expect an automatic billing at the 30%, 60% and 100% of work complete.

    Please give me a solution and how to deal with this requirement.

    She will be grateful, thanks in advance.
    Lanaud

    Hello

    The method of recognition of income called cost to the cost is based on a formula calculated by the extension of the billing. The formula looks at the total of the costs incurred and divides it by the cost of the approved project budget. The formula is the percentage of the cost spent. The model that multiply by the total funds (referenced approved revenue budget) which has recognised the results in total revenue.

    Revenue based progress using the percentage of completion is entered through this form.

    If you want to use the method of cost to the cost that the rule of distribution of project as COST of installation.
    If you want to use your own developed extensions of billing or events entered manually configure rule distribution as EVENT.
    If you want to recognize income from expenses charged to your project, is like a JOB. This method is using bill rates or hourly billing charge of calculating the amount of the income of each item of expenditure.

    Dina

  • Schedule of rates used a project to

    Dear Dina,

    During the preparation of the approved cost budget that I take the named resources and the employee rate schedule will be the rate for me... For some projects, so we go to different as rate schedule tag % (value of hiking)... a project about how can I integrate such scenario in oracle projects?

    Is this possible?

    pls help me thank you n advance...

    Hello

    You can configure as many hourly rates according to the needs. Name of each of them a different title.
    Then assign the appropriate fee to each of your project.

    Dina

  • Is there a way to create a recurring event in Billings of the recipes/projects (r12)?

    Is it possible to create an event/billing revenues in projects that can be planned (charged monthly until a specified end date) other than a customization?

    I think that there is no standard method to do so. However, you can use billing extension to create automatic events. You can set the fields of de FACTO in terms of project or task forces to have a recurring amount and the closing Date which will be recovered in the course of revenue or project to generate project invoices. You can check in that if the event is already created for this month, expansion should not create another event for the same month for this project or extension the task because the user can run the process several times a month. Please note that there is not any history kept for FDF changes for the amount and dates.

    You can decide on other ways of maintaining the recurring amount and end Dates to keep history.

    Waiting for more input from experts.

    Consider the declaration of the User Guide also below:

    *****

    Independent of the transaction

    Once you determine the entries for your calculations, you can determine if your billing extension depends only on other transactions being processed, or if your calculation can be performed without other transactions being processed. Transactions refer to the events and the expenditure items.

    Extensions of billing independent transaction are executed for each project with an assignment of active billing, even if there are no transactions to be processed. This type of billing extension builds about a billable transactions on a project entry. If this entry changes, the calculated Exchange billing amount, which you want to save. For example, the cost-cost revenue allocation method, which relies on the costs and revenues budgeted. If the cost budgeted or projected revenue changes, the amount of income changes. You want to save this amount of revenue change even if no other transaction is processed in the generation of income. This category includes the class extensions billing which calculate revenue and to charge the amounts based on independent values of the amounts included on the project revenue and invoices.

    Note: If you create an extension billing independent operation, he will be executed at each passage of the income or of the invoice process.

    *****

    AB

  • How can I get the green check mark image in APEX?

    How can I get the green check mark Image that appears whenever an action is processed in the APEX?  I use the Application Express 4.2.1.00.08.  I need to add the image of mark in a column on a report that shows the lines that have already been discussed.

    Can someone tell me how to do this?

    I was able to produce the report with the following:

    Select case when Status = 'closed '.

    can ''

    else ''

    end as "completed."

    'ID', 'PROJECT', 'TASKNAME', 'START_DATE', 'END_DATE', 'STATUS', 'ASSIGNED_TO', 'COST', 'BUDGET '.

    TASKS

    Once you add this column of the report, change the properties of the REPORT of the region, then the columns (filled) ATTRIBUTES and change the setting "display as" 'Standard report Column'-, this allows the browser to "make" image compared to only print the text string of the "img" tag