I produced a query based Gantt chart

Select the Null link,

TaskName,

Task_Id,

Parent_id,

actual_start,

actual_end,

progress null,

planned_start,

Planned_End

Of query_table

Everything looks good, except that I don't want to show the progress since we do not actually hold this value. I tried setting it null, as shown above, but it shows up on the table as 0%. Is it possible to remove this display on every spot on the card value?

Thank you

Hello

You will need to customize the XML to achieve this behavior.  On page table attributes, the value "use Custom XML' to Yes and in the XML delete all references to:

Complete: full {%} %

This will remove references to the progress bar in the ToolTips used on the Gantt chart.  Then you will need to update the tag to include information label for the bar.  It looks like the complete label is the default label associated with a project Gantt chart, although I have not found anything in the online documentation indicating this.  I'll follow up with AnyChart on it.  In the meantime, I recommend you read Guide their use online, specifically labels in spots, where you will find information on possible labels, you can set for the bars in the area of the chronology of the graph.  If you leave the tags empty, or simply do not include them, it looks like the bar without any label, which perhaps is the behavior you're trying to reach.  Here is the XML code, you can add to your chart:

.....

.........

.. .or the tags in grey above already exist in the XML table, so should not be copied.  I hope this helps.

Kind regards

Hilary

Tags: Database

Similar Questions

  • See the progress in project Gantt chart adf bar

    Hello

    When I create a project Gantt chart in ADF 12.1.2 alter the properties of the project-> "% complete field" gantt chart I have put the percentage of the task but not illustrated in the chart.

    Show only the date time of the task.

    That's happened?

    Resolved:

    The expected gantt project property in the attribute value type of task is 'Normal' to show the percentage of tasks

  • Problem with the Gantt chart

    I have an Apex 5 with universal theme help

    I want to create a Gantt chart, but I get a syntax error, even though I used the wizard to generate the code

    Select

    null link,

    NAME task_name,

    Task_id ID,

    parent_id null,

    Start_date actual_start,

    End_date actual_end,

    Progress of PROGRESS,

    planned_start null,

    planned_end null

    of 'GUSCRIGHTON '. "" ANG_PROJECT_STAGES ".

    Anyone know what's wrong with the code?

    It works in sql Studio

    Gus

    Gus C wrote:

    I have an Apex 5 with universal theme help

    I want to create a Gantt chart, but I get a syntax error, even though I used the wizard to generate the code

    Select

    null link,

    NAME task_name,

    Task_id ID,

    parent_id null,

    Start_date actual_start,

    End_date actual_end,

    Progress of PROGRESS,

    planned_start null,

    planned_end null

    of 'GUSCRIGHTON '. "" ANG_PROJECT_STAGES ".

    Anyone know what's wrong with the code?

    Probably nothing. I get the same error with a similar request, but after selecting the option Save query without validation when you apply the changes, the graphic is displayed correctly. Potentially, a bug in the validation of the application.

    I'd actually using the region of Gantt plugin found in the application of P-Track packed instead, which is a component of HTML5 more modern which is a better choice for use in the universal theme.

  • Custom color in display Gantt chart based on the State - Apex 4.2

    Hello

    I need to specify the custom color display Gantt chart based on the State.

    Say: Open - Red

    Progress-yellow

    Cancelled - blue

    Closed - Green

    given that the status column is not part of Gantt chart question, how?

    Option color in table attributes is not helping this requirement.

    Kind regards

    Sanjaya

    Hello

    Finally, the problem is resolved with the help of Hilary Farrell-Oraclefantastic example and help anychart pages. This is useful for this URL.

    https://Apex.Oracle.com/pls/Apex/f?p=36648:30:102588100613368:

    http://6.anychart.com/products/anygantt/docs/users-guide/index.HTML?project-Gantt-chart.html

    http://6.anychart.com/products/anygantt/docs/users-guide/index.html?defaults.html

    -Sanjaya

  • How to disable display of work orders-> frame in view dependency-> Gantt chart display image file

    Hi all

    We want to hide a feature stopped working screen in Oracle EBS R12.1.3 is Gantt chart displays by application. This is a png image file, and thousands of files are generated daily.

    The image is accessible from screen-> view dependency framework work orders-> show image file-Gantt chart

    Thank you.

    YM

    Fact through customization of forms.

  • Gantt chart is not correctly displayed for the task to the foreground

    Hello

    I tried to create a Gantt chart similar to [http://www.anychart.com/products/anygantt/gallery/sample_02.html]
    except the connectors aren't needed. I could stall parts of the custom XML part, but the parent tasks always appear with the same style as the tasks of the child. I want to do the parent display periods so that they are different compared to the periods of child as in the example graph, where they are gray and thinner. How is that possible?

    Tiina

    Tiina salvation,

    First of all, just to explain the current behavior, generated in APEX chronology in the diagrams of Gantt bars have a style by default called defaultStyle applied to them. This style controls the appearance of the different elements of the region of the timeline, as the current bar, progress bar color etc. The needs of default style to apply to the tags in the table XML that is tags containing the data of your Gantt chart. To allow users to control the appearance of objects timeline via attributes on the page attributes of table, we update the Style by default with the selected page attributes of table values and then we reference this style in the tag, as follows:

    
      
        
      
    
    

    .. .or style = "defaultStyle" is the reference to the style. If you look in the XML file, you will see where the default Style has been set. Tags are generated during execution and filled with the results of the query in the chart series game. If we apply a default style to these tags, then users must manually generate the tags themselves in order to apply a style to their data in Gantt chart.

    In AnyChart, no style has been applied to the example you have selected - http://www.anychart.com/products/anygantt/gallery/sample_02.html - only default AnyChart parameters are used here. Due to the existence of style = "defaultStyle" in your Gantt chart data, you will need to make the necessary changes in the tags of your XML file. These changes are possible via the options on the page attributes of table or by customizing the XML. I know that's not exactly the same as the example of AnyChart, but you can get something similar just update the graphic attribute settings, as in this example: http://apex.oracle.com/pls/apex/f?p=36648:50. I hope this helps.

    Kind regards
    Hilary

  • APEX 4.0 - construction of Gantt chart error?

    Hello world

    When I build a Gantt chart in apex.oracle.com, the start and end dates show no actual date, just text "dd.mm.rr".
    My query follows:

    Select
    NULL as link,
    Description like taskname,
    TASK_ID as task_id,
    NULL as parent_id,
    start_date as actual_start,
    End_date as actual_end,
    progress as progress
    of PENDING_TASKS;

    Any ideas?

    Oscar

    Hi Oscar,.

    For Gantt diagrams, by default the Format of Date of Application will use to bring in the form the dates on your Gantt chart. If a date of application-level format is not specified and none is a Date of the Gantt chart format, via the attributes list page, then the NLS_DATE_FORMAT will serve to shape the dates on your Gantt chart. If you want to set a date through the table attributes page format, change your Gantt chart and update the item "Date" in the region of Gantt chart settings. For example, on this example on apex.oracle.com - http://apex.oracle.com/pls/apex/f?p=36648:4 - I put the 'Date Format' * % dd.%MMM.%yy*, which uses the AnyChart format specifiers required, indicated such in the AnyChart documentation, specifically in the list of parameters of formatting: http://www.anychart.com/products/anygantt/docs/users-guide/locale.html?fromtree#list.

    Version 4.0 - post, I identify a problem with the context menu associated with the element 'Format of Date' on page table attributes and bug 9861439 can be used to track this issue. A fix for this issue will be available in our next release, but in the meantime you can enter dates in the text 'Format of Date' element, ensuring that you use the format specifiers AnyChart described in the documentation that I have included a link for above example * % dd.%MMM.%yy*.

    I hope this helps.

    Kind regards
    Hilary

  • Chronology in the Oracle Apex5 Gantt Chart view

    Hi all

    I'm developing an application using Oracle Apex 5.

    I have a created a page with graphic Flash-> Gantt chart.

    He created as below

    1.png

    But I need to make as below

    2.png

    How to do this?

    Su.GI wrote:

    I'm developing an application using Oracle Apex 5.

    I have a created a page with graphic Flash--> Gantt chart.

    He created as below

    But I need to make as below

    How to do this?

    In the component graphic Flash Gantt this requires a graphical change settings using the XML part that is customized according to the documentation AnyGantt 4.3. In the area of the Gantt chart, switch to Use Custom XML Yesand modify the XML custom, expanding the timeline element of

    ...
            
                
            
    ...
    

    to include a custom scale element which eliminates the level of the day:

    ...
            
                
                
                  
                    
                    
                    
                    
                    
                    
                  
                
            
    ...
    

    A better alternative would be to use the Gantt chart plugin region of the packed app P-way rather than the Flash option integrated Gantt chart. The plug-in supports simple customization/user control in the period of mounting using a page item control.

  • View gantt chart, based on the value of IR - apex 4.2

    Hello

    There is a diagram of Gantt chart below that an IR is there. (see data).

    If the user filter IR, we must show only that the entries that are displayed in IR, in the Gantt chart.

    How can achieve us?

    Kind regards

    Sanjaya

    The problem is solved with the help of Denes Kubicek blog.

    http://deneskubicek.blogspot.in/2013/05/getting-interactive-report-query.html

    Thank you

    Sanjaya

  • Links page of Gantt chart open in modal window

    Hello.

    We use Gantt chart with column of link diagrams which open in detail table in the new page - according to this line of clicked gantt.

    Each row in the gantt chart may open a different page.

    Is it possible to open the new page (when the link is clicked) in the modal window?

    We use the apex 4.2.5.

    Thank you.


    Kind regards

    Dejan

    Hi Dejan,

    You had the largest part of the correct configuration. I finished the example.

    1 / the LINK column added to the query of the series.

    2 / in the series, I specified the link attributes. The URL used is: javascript:setURLForModal('#LINK#').

    3 / the raised event was a typo in it. Correct it.

    4 / the dynamic action is triggered on the issue, not on the region. The attribute must be data-url and not data_url

    The example works now. Œuvres pretty cool and it's almost all defined by their Summit.

  • Apex 4.1 - Gantt chart resource with dynamic colors based on the background

    Hello

    I request of the customer to create a resource of Gantt chart that displays the different color bars based on the employee assigned to each task.

    I found two excellent examples of Hilary on the use of different colors; Unfortunately, they use static colors:

    https://Apex.Oracle.com/pls/Apex/f?p=36648:114

    https://Apex.Oracle.com/pls/Apex/f?p=36648:60

    I will present an example for the http://apex.oracle.com later in the day.

    Meanwhile, does anyone have a suggestion on how to do this?

    Thank you

    Erick

    Erick,

    What makes you decide to use a chart of the resource instead of a task of projects, so what you are viewing is just a chart of the project? No resource is indicated on the data grid, but rather task names. Not not it doesn't, but it's confusing that shouldn't be there. It complicates the xml code required when it should not.

    Aside from that, you can do what you want, but you need to change the custom XML and generate xml data yourself.

    See page 2 in your application: https://apex.oracle.com/pls/apex/f?p=16559:2

    -generate xml processes

    -region with a few hidden items

    -custom xml to include items hidden in the correct places

    -remove the series just to indicate that no data is retrieved in a way

    In short:

    -generate xml data to generate a style for every single transferee. I generate a name for each "style" | assignee_id, which makes it easy to reference in the task. I added a function to generate a custom hex color too, just for the joy?

    -generating resources

    -generate periods and assign the style accordign to the assignee

  • Can we create Gantt chart using BI Publisher plug-in

    Hi Evereyone,.

    I'm working on a report that requires the Gantt chart to be published by unify. I use the BI Publisher MS Word and Excel plugin.

    Has anyone tried this before. It will be useful if you can share the steps or any other site which deals with creation of Gantt chart.

    Thank you

    It is possible. See this site for a starting point: https://blogs.oracle.com/xmlpublisher/entry/getting_gantty

    Basically, you create a table where each row represents an activity from your calendar sheet. You will need a space of great column for the Gantt chart and add a few MS Word forms (rectangles).

    If you play with and you can move the bar and size correctly. Download the appropriate shifts and durations in your data SQL view.

    This is the easiest part. The hardest part is to show the dates (weeks/months/years) at the top of your table with spacing on the right... It is actually easier to just the dates of beginning and end of each line.

    -It should be noted that showing the relationships between activities (ie. the lines connecting the bars) cannot be done in BI Publisher. If it is a requirement, I suggest that investigate you other approaches. You can list predecessor and successor activity in the form of column ID in your table instead.

    Hope that helps,

    The f

  • Grid in Gantt chart

    Hello

    It is a problem with a Gantt chart that is part of an Apex application I support. It uses the format to_timestamp (DD-MON-RRRR hh: mi) to retrieve the data and display in the Gantt chart. The only problem is that since I use the format HH and AM not HH24 all the time is displayed in 12-hour format the component "hour" of the x_axis chart seems to be assuming that time is always. Is there anyway to fix this, or simply change the x_axis to show say 05:00 instead of 17:00?

    Thank you

    His assuming that all times are AM because you forgot to tell the to_timestamp() function if time is or h... so, it must assume that it is always AM.

    Your date/time data must be stored in a DATE data type.

    Use the CAST (columname AS TIMESTAMP) operator if it is already a DATE instead of using to_timestamp (to_char ())

    MK

  • Order of the Gantt chart

    Hello

    I created a Gantt chart and discovered a problem. Jobs don't always appear in chronological order.

    I tried to order the query by date, but then the tasks don't always show next (or in the same order) on the bars to the right of the plan.

    Is anyway I can order the tasks without losing the alignment with the diagram of the individual task bar?

    Thanks in advance.

    Hello

    You have not specified what type of Gantt chart, you use: it is a project gantt chart or resource? In addition, you are dealing with hierarchical data?

    Looks like you might be dealing with hierarchical data and the order in which the data are generated is cause your problem and culminating in the timeline entries being out of alignment with the datagrid control.  So, without seeing the application in use, my suggestion would be to update the query to generate a hierarchical representation of your data via an START WITH... CONNECT BY question, using a syntax similar to the following:

    Select the link,
    TaskName,
    ID,
    parent_id,
    start_date,
    End_date,
    status
    tasks _table
    Start by parent_id is null
    connect by parent_id = prior id
    siblings arrested by start_date

    If the query is retrieving the list of tasks and then hierarchically by listing the based on parent-child association which was held in the PARENT_ID of the table column.  The end result means that each parent task is listed with their tasks associated with children and sorted by START_DATE.

    If this isn't answering your query, please update this thread with more information about your test scenario.  Even better - if you could create a unit test on apex.oracle.com and post a link to the unit test and the syntax of the query you are using, it would be very useful.

    Kind regards

    Hilary

  • Scheduling Gantt Chart - highlighting of modified duties

    We strive to implement our Gantt chart behavior as on the actions of the user like drag-and-drop, changes are not immediately committed to the database.

    We ask a commit on the transaction to save all changes when the user presses a button 'save'.

    However, we would like to highlight modified (for example, the extended duration task) duties in a different color to keep track of all the actions of the user, while the changes are not yet validated.

    Commit, all jobs must go back to the default color.

    I'm doing it with the TaskbarFormatManager, but can't find a way to use it for this particular requirement.

    Can I use a column in my table to map the type of task for the Gantt chart, and how to upgrade this attribute in my VO / Gantt chart when a task is changed?

    I managed to solve this problem quite awhile, but I forgot to post the solution.

    I have added a transitional attribute to my entity object.

    <>

    Name = "TaskChanged".

    ColumnName = "" $aucun$ ""

    SQLType = 'VARCHAR '.

    Type = "Java.lang.String"

    ColumnType = "" $aucun$ ""

    IsQueriable = "false".

    IsPersistent = "false" / >

    In the entity bean Get accessor method.

    public String getTaskChanged() {}

    If (this.getEntityState () is EntityImpl.STATUS_MODIFIED)

    return "CHANGED";

    If ((String) getAttributeInternal (TASKCHANGED) is nothing)

    on the other

    'CLEAN '; return

    }

    Add this attribute of the entity object to the original Version. The application of VO is unchanged.

    In the Gantt chart in the jspx, I put the Task Type to the attribute TaskChanged.

    And the code for TaskbarFormatManager is as usual:

    public TaskbarFormatManager getFormatManager() {}

    TaskbarFormatManager _manager = new TaskbarFormatManager();

    _manager.registerTaskbarFormat ("CHANGE", TaskbarFormat.getInstance ("gold", UISchedulingGantt.GOLD_FORMAT));

    _manager.registerTaskbarFormat ('CLEAN', TaskbarFormat.getInstance ("blue", UISchedulingGantt.STEEL_BLUE_FORMAT));

    Return _manager;

    }

    When the validation is called when the click on the "Save" button, the entity is no longer in an altered state, and all the recorded tasks back to the steel blue format.