Date of PRESSING: limited to a date in SO schedule
Hi allI tried to program a client command, but it is limited to this day as (31-dec-2008), I can't change this date. Is there any facility for, why date is limited to a date specified? Help, please.
Thank you
Shishir
It seems you may have activated ATP. Define the profile according to yes and try again
OM: Authorized to substitute the ATP.
Tags: Oracle Applications
Similar Questions
-
My environment is running v6.2.1.415 tide in Windows.
Recently, I was able to receive more processors to the computer (and memory) for both servers - the Client Manager and tide Master.
My environment was not in fact considered environment tide (due to the size of the database), "medium" because of the number of jobs on a daily basis and/or users running clients.
Looking at the Performance Tuning Guide 6.2.1, she suggests to place some more recent values in three files:
--
[1] Master.Props,.
[2] Clientmgr.props and
[3]-6.0.0.0.dsp
--
But the most funny about this, is that the file-file 6.0.0.0.dsp does not exist.
Someone at - he had this situation before? How do solve you? (Don't you worry about this?)
In addition, is the only way the changes - is to turn off the two services, make the changes, and then turn on services?
Or can I make configuration changes, and then stop and start the two services (master and client Manager)?
Thanks in advance-
Hi Dave,.
The performance guide uses an arbitrary name for the dsp - Data Source Provider / plugin CM. This file is located in your Customer Manager-config-*.dsp
Backup of all your accessories and all the PSD files. It is best to stop the Client Manager, and master, make configuration changes, then launch Master, then the Client Manager. Online changes don't usually end up too well.
Kind regards
The Derrick
-
Export data pump job scheduler does not load
I have a pump a 10.2.0.2.0 data dump file database, and then import on 11.2.0.3.0 fails with this error:
ORA-39083: Object type PROCOBJ failed to create with error: ORA-06502: PL/SQL: numeric or value error: character to number conversion error Failing sql is: BEGIN dbms_scheduler.create_job('"MY_JOB_NAME"', job_type=>'STORED_PROCEDURE', job_action=> 'MY_SCHEMA.MY_PROCEDURE' , number_of_arguments=>0, start_date=>'31-JUL-12 02.05.13.782000 PM EUROPE/BERLIN', repeat_interval=> 'FREQ=WEEKLY;BYDAY=FRI;BYHOUR=7;BYMINUTE=0;BYSECOND=0' , end_date=>NULL, job_class=>'"DEFAULT_JOB_CL {code} I extracted the SQL Code from the dump file and it looks like this: {code} BEGIN dbms_scheduler.create_job('"MY_JOB"', job_type=>'STORED_PROCEDURE', job_action=> 'MY_SCHEMA.MY_PROCEDURE' , number_of_arguments=>0, start_date=>'31-JUL-12 02.05.13.782000 PM EUROPE/BERLIN', repeat_interval=> 'FREQ=WEEKLY;BYDAY=FRI;BYHOUR=7;BYMINUTE=0;BYSECOND=0' , end_date=>NULL, job_class=>'"DEFAULT_JOB_CLASS"', enabled=>FALSE, auto_drop=>FALSE,comments=> 'bla bla comment' ); dbms_scheduler.set_attribute('"MY_JOB"','logging_level','HIGH'); dbms_scheduler.enable('"MY_JOB"'); COMMIT; END; / {code} After the job is defined the second statement fails: {code} SQL> exec dbms_scheduler.set_attribute('"MY_JOB"','logging_level','HIGH'); BEGIN dbms_scheduler.set_attribute('"MY_JOB"','logging_level','HIGH'); END; * ERROR at line 1: ORA-06502: PL/SQL: numeric or value error: character to number conversion error ORA-06512: at "SYS.DBMS_SCHEDULER", line 2851 ORA-06512: at line 1 {code} From the source I see: {code} SQL> select logging_level from dba_scheduler_jobs where job_name = 'MY_JOB'; LOGG ---- FULL {code} In the docs I see these valid LOGGING_LEVELs: http://docs.oracle.com/cd/E14072_01/server.112/e10595/scheduse008.htm#CHDFDFAB DBMS_SCHEDULER.LOGGING_OFF DBMS_SCHEDULER.LOGGING_FAILED_RUNS DBMS_SCHEDULER.LOGGING_RUNS DBMS_SCHEDULER.LOGGING_FULL So please help me, I can't find something useful on MOS, what is Data Pump exporting there, and can not import it again Maybe I have overseen a known bug?
Finally I found the bug myself:
MOS: Impdp of objects of treatment fails with ORA-39083 and ORA-06502 [ID 780174.1]
https://support.Oracle.com/epmos/faces/DocContentDisplay?ID=780174.1
-
Automate the process of loading data using Task Scheduler
Hello
I do the automated processes to load the data into Hyperion Planning application with the help of the Task Scheduler.
I created Data_Load.bat file, but the rest of the process, I cannot complete.
So could you help me, how to automate the loading of the process data using the file Data_load.bat & Task Scheduler.
Thank youWindows 2008? Open the Task Scheduler, Action > creates a fundamental task, give it a name, select the frequency, select start a program, find the batch script, then you're pretty much done for a basic task.
See you soon
John
http://John-Goodwin.blogspot.com/ -
Instantis project and the Phase Dates
Is it possible to link the project and dates for the activities under Phase of their planning?
Can you not make the dates don't defer?
Instantis schedules Oracle roll in the traditional way. Normally, when someone creates your calendar templates, add it to the effort and the duration of the child of the tasks for the summary tasks or phases. The project leader can keep these totals to date in their schedules.
If your activities are related to the use of dependencies, Instantis can be used to recalculate all the dates and the hours that remain for activities (annex manage > Project reschedules > calculate the Dates [and update Plan or Plan/Baseline]). This should keep your calendar up-to-date.
-
Change of account with API data
Hey guys,.
Could you advise me on a good way to handle this situation: IOM reconciles a user of a system of human resources and which identifies the user has accounts on a target system. He reconciles a user account, but there could be a situation when the IOM must change this account according to the user attributes reconciled.
Is there a clever way to push the user attributes to a target system? I don't really want to go and check if the attributes have different values in the target system and IOM. I wonder if there is a way to 'trigger' population of values from a user to an account?
Thank you
Philipp
Hello
Your requirement is something like:
(1) assume that HR system got to the last name= Grig and even was closer to IOM user profile
(2) after that you make your target AD recon and your form process becomes value of name as Grig1
(3) now, you want to change the target attribute AD for GRIG family name?
Its very common number in any implementation of the IOM. But no one cares mainly on this issue as the problem of erroneous data and not something that IOM should takecare.
As a correction of the data activity, triggers are not available to check something like that.
I will propose better write a custom Scheduler and compare the value of the IOM user profile and account (form of course) and if the value of form for the process account is false then make API change the call to update the correct value on the shape of course. This will update the target attribute value as well.
Since there should be a correction of data time activity Scheduler is therefore best to think of something else.
~ J
-
Determine the next deadline Date
I have a table that contains the definition of the schedule, a schedule defines when a document should be submitted to a specific part. The definition of annex contains a start date and end date, a type of recurrence (is pointed it out a time or on a recurring schedule) and the frequency to which the document should be filed. The second table provides a history of comments, this option stores while it was due and when it was received. Earlier this month, pre-fill us the layout table with a list of records that will be due for the month. For example, on 1 September look us through all schedules and determine which ones would have a record due to a certain point in the 9/12 and then to create a record in the presentation table.
I have questions, the calculated the tender documents list to work properly.
The DDL and DML will be in a follow up post
Here's the query I use currently and is unable to work properly.
Basically I found all possible records in the table in the annex that could have a record expected in September, and then generate a result for all possible instances and then look at only those whose calculated due date is 01/09/2012. I have determined that the root problem, I have right now is this line:with schedules as ( -- generate a list of valid permit schedules select s.schedule_id,s.submittal_frequency_months,s.recurrence_type, s.first_due_date,s.requires_approval, round(round(months_between(to_date('09/01/2012','mm/dd/yyyy'),s.first_due_date))/decode(s.submittal_frequency_months,0,1,s.submittal_frequency_months)) recurrence_number from permit p join schedule s on (p.permit_id=s.permit_id) where p.permit_id=nvl(:p_permit_id,p.permit_id) and p.permit_status_type_id=1 -- only active permit and s.recurrence_type in ('One Time', 'Recurring') -- submittals with a defined schedule and coalesce(s.last_due_date,sysdate) >= sysdate -- only submittals whose last due date has not passed, null last date included and trunc(s.first_due_date,'mm') <= to_date('09/01/2012','mm/dd/yyyy') -- only valid start dates --and round(round(months_between(to_date('09/01/2012','mm/dd/yyyy'),s.first_due_date))/decode(s.submittal_frequency_months,0,1,s.submittal_frequency_months)) >0 ) -- create a list of all potential due dates for these schedules select submittal_id_seq.nextval,schedule_Id,8,requires_approval, case when recurrence_type='One Time' then first_due_date when recurrence_type='Recurring' and trunc(first_due_date)=to_date('09/01/2012','mm/dd/yyyy') then first_due_date else add_months(first_due_date,(submittal_frequency_months*d.iteration)) end next_due_Date,user,sysdate,user,sysdate from schedules cross join (select level iteration from dual connect by level <= (select max(schedules.recurrence_number) from schedules)) d where schedules.recurrence_number <=d.iteration and trunc(case when recurrence_type='One Time' then first_due_date when recurrence_type='Recurring' and trunc(first_due_date)=to_date('09/01/2012','mm/dd/yyyy') then first_due_date else add_months(first_due_date,(submittal_frequency_months*d.iteration)) end,'mm') = to_date('09/01/2012','mm/dd/yyyy') -- limit the records to the date in question and not exists (select null from submittal sub where sub.schedule_id=schedules.schedule_id and trunc(sub.due_date,'mm')=to_date('09/01/2012','mm/dd/yyyy')) -- exclude those that already have a submittal record ;
(select level iteration of double connect by level < = (select max (schedules.recurrence_number) of planning)) d
ID of the 469907 planning has a start date of 15/05/1992 and a frequency of all 2 months. I calculate what I call the number of recurrence, i.e. the number of times that the calendar has occurred since its beginning now. I use to make a calculation of add_months from the start date and then finally compare the start dates of these calculated with my month of target (09/12). In this one case records the calculated number of recurrence is 122. Then when I generate the connect by level is 122 records for each schedule, so I end up with duplicate records in the presentation for many schedule table. This current request could probably work if I could find a way to make the specific annex level ID, but I did not that far.
Besides the fact that it returns erroneous results, I think that there must be a better, more efficient method to determine which records are due for a given month. I thought there are probably some great way to use the clause type here, but I don't have a knowledge on that one yet.
If you run the insert statement what follows, you will see that it inserts more than 2,400 records:
You can see the problem after the words:insert into submittal (submittal_id,schedule_id,submittal_status_type_id,requires_approval,due_date,created_by,created_date,modified_by,modified_Date) with schedules as ( -- generate a list of valid permit schedules select s.schedule_id,s.submittal_frequency_months,s.recurrence_type, s.first_due_date,s.requires_approval, round(round(months_between(to_date('09/01/2012','mm/dd/yyyy'),s.first_due_date))/decode(s.submittal_frequency_months,0,1,s.submittal_frequency_months)) recurrence_number from permit p join schedule s on (p.permit_id=s.permit_id) where p.permit_id=nvl(:p_permit_id,p.permit_id) and p.permit_status_type_id=1 -- only active permit and s.recurrence_type in ('One Time', 'Recurring') -- submittals with a defined schedule and coalesce(s.last_due_date,sysdate) >= sysdate -- only submittals whose last due date has not passed, null last date included and trunc(s.first_due_date,'mm') <= to_date('09/01/2012','mm/dd/yyyy') -- only valid start dates --and round(round(months_between(to_date('09/01/2012','mm/dd/yyyy'),s.first_due_date))/decode(s.submittal_frequency_months,0,1,s.submittal_frequency_months)) >0 ) -- create a list of all potential due dates for these schedules select submittal_id_seq.nextval,schedule_Id,8,requires_approval, case when recurrence_type='One Time' then first_due_date when recurrence_type='Recurring' and trunc(first_due_date)=to_date('09/01/2012','mm/dd/yyyy') then first_due_date else add_months(first_due_date,(submittal_frequency_months*d.iteration)) end next_due_Date,user,sysdate,user,sysdate from schedules cross join (select level iteration from dual connect by level <= (select max(schedules.recurrence_number) from schedules)) d where schedules.recurrence_number <=d.iteration and trunc(case when recurrence_type='One Time' then first_due_date when recurrence_type='Recurring' and trunc(first_due_date)=to_date('09/01/2012','mm/dd/yyyy') then first_due_date else add_months(first_due_date,(submittal_frequency_months*d.iteration)) end,'mm') = to_date('09/01/2012','mm/dd/yyyy') -- limit the records to the date in question and not exists (select null from submittal sub where sub.schedule_id=schedules.schedule_id and trunc(sub.due_date,'mm')=to_date('09/01/2012','mm/dd/yyyy')) ;
Tonyselect schedule_id,count(0) from submittal where trunc(due_date,'mm')=to_date('09/01/2012','mm/dd/yyyy') and submittal_status_type_id=8 having count(0) >1 group by schedule_id;
Hello
I think you want something like Bob solution. To avoid any computation MONTHS_BETWEEN again and again, you can do it once, in a subquery, like this:
WITH got_month_num AS ( SELECT schedule_id, rec_type, rec_months, first_due_date , MONTHS_BETWEEN ( TRUNC (SYSDATE, 'MONTH') , TRUNC (first_due_date, 'MONTH') ) AS month_num FROM schedule -- WHERE ... -- If you need any filtering, put it here ) SELECT schedule_id, rec_type, rec_months, first_due_date , ADD_MONTHS (first_due_date, month_num) AS this_due_date , FLOOR ((month_num + 1) / rec_months) AS iteration FROM got_month_num WHERE MOD ( month_num , CASE WHEN rec_type = 'Rec' THEN rec_months ELSE month_num + 1 END ) = 0 ;
The WHERE clause in the main query ensures that you will only get results that have a current month end_date.
Using the sample data that Bob posted, the result is:
SCHEDULE_ID REC REC_MONTHS FIRST_DUE THIS_DUE_ ITERATION ----------- --- ---------- --------- --------- ---------- 4 One 1 16-SEP-12 16-SEP-12 1
Schedule_id = 1 is not due until January and schedule_id = 2 is not due until November.
Published by: Frank Kulash, Sep 12, 2012 13:08
Column corrected iteration. (You can't that column, anyway.) -
code succcessive to genereate difference between dates in a table
First create and insert statements;
The output of the table of the ANNEX should be now like this:create table schedule(iloan_code number , schedule_date date); insert into schedule values(1001, to_date('01-jun-2012')); insert into schedule values(1001, to_date('01-jul-2012')); insert into schedule values(1001, to_date('01-aug-2012')); insert into schedule values(1001, to_date('01-sep-2012')); insert into schedule values(1001, to_date('01-oct-2012')); commit;
We want an additional column by name as well as the existing columns DAYS that would be the difference between dates.ILOAN_CODE SCHEDULE_DATE 1001 01-JUN-12 1001 01-JUL-12 1001 01-AUG-12 1001 01-SEP-12 1001 01-OCT-12
First line should be the difference between sysdate as well as the date of June 1, 2012 and successive lines must be the difference between successive calendar date
For example in the second row the DAYS column should represent the difference between 1 July 2012 and 1 June 2012 and so on for the following ranks too.
We need get the result by a SELECT statement
The output of the table in the ANNEX must be something like that.
Please notify;iloan_code schedule_date days Logic which we need 1001 1-Jun-12 22 sysdate-1st June 2012 1001 1-Jul-12 30 difference between 1st July 2012 and 1st June 2012 1001 1-Aug-12 31 difference between 1st aug 2012 and 1st July 2012 1001 1-Sep-12 31 difference between 1st sep 2012 and 1st aug 2012 1001 1-Oct-12 30 difference between 1st oct 2012 and 1st sep 2012
Hello
You can change the Hoek solution like this:
SELECT iloan_code , schedule_date , schedule_date - LAG ( schedule_date , 1 , TRUNC (SYSDATE) ) OVER (ORDER BY schedule_date) AS days_between FROM schedule ORDER BY schedule_date ;
If all schedule_dates will be after SYSDATE, then you need not the CASE expression to test if it is.
The argument optional 3rd to LAG is a return value in case there is no previous line.Sri says:
... The output of the table in the ANNEX must be something like that.iloan_code schedule_date days Logic which we need 1001 30-Jun-12 07 sysdate-30June 2012 1001 1-Jul-12 30 difference between 1st July 2012 and 30 June 2012 ...
The difference between 30 June 2012 and July 1, 2012 is not only 1 day?
-
Stuck with trying to get a decode to match data
I have this little bit of SQL:
The idea is that the "ECS" contains information of planning, where 31 1 numbers represent the days of the month.WITH sampledata AS (SELECT '000000000000000000000000000000000010101' schd FROM DUAL union all SELECT '000000000000000000000000000000001111111' sch from DUAL union all SELECT '101000000000100000000000000000000000000' sch from DUAL union all SELECT '000000000000000000000000000000010000000' sch from DUAL) SELECT schd , sign(to_number(substr(schd, 33))) c0 , substr(schd, 33) c01 , substr(schd, 3, 1) c02 , decode(sign(to_number(substr(schd, 33))), '1', 'Days of week: ' || decode(substr(schd, 33, 1), '1', 'Su ') || decode(substr(schd, 34, 1), '1', 'Mo ') || decode(substr(schd, 35, 1), '1', 'Tu ') || decode(substr(schd, 36, 1), '1', 'We ') || decode(substr(schd, 37, 1), '1', 'Th ') || decode(substr(schd, 38, 1), '1', 'Fr ') || decode(substr(schd, 39, 1), '1', 'Sa ')) c1 , decode(substr(schd, 32, 1), '1', 'Last day of month ', '0', decode(sign(to_number(substr(schd, 33))), '1','Days of week: ' || decode(substr(schd, 33, 1), '1', 'Su ') || decode(substr(schd, 34, 1), '1', 'Mo ') || decode(substr(schd, 35, 1), '1', 'Tu ') || decode(substr(schd, 36, 1), '1', 'We ') || decode(substr(schd, 37, 1), '1', 'Th ') || decode(substr(schd, 38, 1), '1', 'Fr ') || decode(substr(schd, 39, 1), '1', 'Sa '), '0','Set Days of Month: ' || decode(substr(schd, 1, 1), '1', '1st ') || decode(substr(schd, 2, 1), '2', '2nd ') || decode(substr(schd, 3, 1), '3', '3rd ') || decode(substr(schd, 4, 4), '4', '4th ') || decode(substr(schd, 5, 5), '5', '5th ') || decode(substr(schd, 6, 1), '6', '6th ') || decode(substr(schd, 7, 1), '7', '7th ') || decode(substr(schd, 8, 1), '8', '8th ') || decode(substr(schd, 9, 1), '9', '9th ') || decode(substr(schd, 10, 1), '10', '10th ') || decode(substr(schd, 11, 1), '11', '11th ') || decode(substr(schd, 12, 1), '12', '12th ') || decode(substr(schd, 13, 1), '13', '13th ') || decode(substr(schd, 14, 1), '14', '14th ') || decode(substr(schd, 15, 1), '15', '15th ') || decode(substr(schd, 16, 1), '16', '16th ') || decode(substr(schd, 17, 1), '17', '17th ') || decode(substr(schd, 18, 1), '18', '18th ') || decode(substr(schd, 19, 1), '19', '19th ') || decode(substr(schd, 20, 1), '20', '20th ') || decode(substr(schd, 21, 1), '21', '21st ') || decode(substr(schd, 22, 1), '22', '22nd ') || decode(substr(schd, 23, 1), '23', '23rd' ) || decode(substr(schd, 24, 1), '24', '24th ') || decode(substr(schd, 25, 1), '25', '25th ') || decode(substr(schd, 26, 1), '26', '26th ') || decode(substr(schd, 27, 1), '27', '27th ') || decode(substr(schd, 28, 1), '28', '28th ') || decode(substr(schd, 29, 1), '29', '29th ') || decode(substr(schd, 30, 1), '30', '30th ') || decode(substr(schd, 31, 1), '31', '31st ') ) ) schedule FROM sampledata;
The 3rd line of the sample data contains a schedule reports to run on the 1st, 3rd and 13th of the month.
The SQL returns a match for the 1st of the month, but it does not pick up the calendar for the 3rd or the 13th of the month.
I thought that since the SQL for the 'calendar' column, that he would return to the 3rd, but it's not to do it, even if the "C02" pass, I can confirm that the value for the 3rd the long is a character, I thought I would be be recognized / corresponding to this line:
All advice very much appreciated, thanks!decode(substr(schd, 3, 1), '3', '3rd ') ||
PS - I know the code is probably very awkward with my big long list of decodes to the days of the month, but I'm not smart enough for a smoother road!Maybe
decode (substr (ECS, 3, 1), '1', '3').
Instead of
decode (substr (ECS, 3, 1), '3', '3').Concerning
Etbin
-
Released on region calendar Date format
I have a stupid problem (stupid on my part). I have a region of calendar on one of my pages, and I'm trying some additional information about each release date. The SQL code that I use to collect the data of the schedule is:
Select
participant_id,
participant_name,
visit_description,
assigned_team,
sched_dttm sched_time,
sched_dttm
of home_visits_vw
order of sched_dttm
(Yes, I have sched_dttm twice, because the ultimate goal is to display the time of the appointment on the monthly view and have a separate field that contains just the date to be used as a control break.)
The place where I need help is after running the command, in the format column in the calendar section, I try to display the time. The code I use is:
#PARTICIPANT_NAME # < here > (#VISIT_DESCRIPTION # / #ASSIGNED_TEAM # / #SCHED_TIME #) < here > < here >
How do I truncate or mask format sched_time in the SQL part or the area of column format for just having the time display instead of the entire date?
Thank you.
JoshHi Josh,.
Modify the SQL code to use TO_CHAR that displays all the time, i.e.
Select
participant_id,
participant_name,
visit_description,
assigned_team,
To_char(sched_dttm,'HH24:mi:SS') sched_time,
sched_dttm
of home_visits_vw
order of sched_dttmConcerning
Paul
-
Cannot install Windows device recovery tool in Windows 7
I can't install the NOKIA SOFTWARE recovery tool v 6.0.3 in my laptop that is running Windows 7, 64-bit. I get error 0 x 80070002 system cannot find the specified file. I have rights full administrator on my laptop, and I've already scanned my laptop for malware and viruses (clean).
Hi Nagendra,
Sorry for the inconvenience caused.
You can refer to the link below and check the details of the error message.
https://support.Microsoft.com/en-us/KB/201318
Are you using Windows phone Device Recovery Tool?
What application or antivirus security suite is installed and your current subscription? What anti-spyware (other than Defender) applications? What third-party firewall (if applicable)?
I suggest you to disable the third-party antivirus and check if it helps.
WARNING:
Antivirus software can help protect your computer against viruses and other security threats. In most cases, you should not disable your antivirus software. If you need to disable temporarily to install other software, you must reactivate as soon as you are finished. If you are connected to the Internet or a network, while your antivirus software is disabled, your computer is vulnerable to attacks.
This error could be the side server. I suggest you try to install it after awhile.If the problem persists, you can try the mentioned method and check if it helps.You can try to perform the check disk error on your computer using the chkdsk.exe tool command line and check if that helps.
CHKDSK (Chkdsk.exe) is a command-line tool that checks volumes for problems. The tool tries to repair any that it finds.Important: While performing hard disk drive error checking, if bad sectors can be found, the available data on this sector may be lost when tried to repair.1. click on start, run, type cmd and then click OK. A command prompt window opens.
2. type chkdsk /f /r and press ENTER.
You are prompted to schedule Chkdsk to run when the computer restarts.
3. tap on it and then press ENTER.
4 restart your computer. At startup, Windows will scan your disk for errors, and Windows will try to recover any files that are located on areas damaged the disk.For more information http://support.microsoft.com/kb/884070 (this item can also be used for windows 7)
Hope this information is useful. Back to us for other queries. We are happy to help you!
-
I greeted Windows download and install updates automatically. The schedule is fixed weekly Monday morning at 01:30. I don't think that it has never updated right here. Today Tuesday at about 19:45 so I watched some video on the internet that the computer begins to download the updates and severely slowing down throughout the system. The browser was insensitive and Explorer then hang because I tried to close my browser and must be restarted. My question is why windows is not up-to-date at the scheduled time? Is there a reason windows slow down my system while I use it?
Hi Frogg420,
We cannot set the update interval of 30 minutes or 15 minutes. We can only it mounted 01:00 or 02:00 / pm. I suggest you to check with windows update settings. You can check the link below:Windows Update: http://www.microsoft.com/windows/downloads/windowsupdate/learn/windowsvista.mspx
Even check for the BITS (Background Intelligent Transfer service) service. Follow the steps for the same:
i. Click Start
II. in the search box type in services.msc and open services window
III. Locate the Background Intelligent Transfer service
IV. right click on the service
v. If the service is stopped and then starts the service
VI. to start the service, click and select Properties
VII. and in startup type, select automatic
Windows update downloads in the background and does not affect the Internet connectivity or your work.
With regard to:
Samhrutha G S - Microsoft technical support.
Visit ourMicrosoft answers feedback Forum and let us know what you think.
-
Why isn't my default calendar setting - economy - to defragment maintenance?
I managed to get Defrag to work. But when I set the schedule, & check the "dun recommend the calendar" box-it reads to get an update for regular maintenance. However, when I close the box & reopen, the date of "next schedule run" - said '' never. ''
How can I set this default?
Dawn Harvey JHello
1 did you change on your computer?
2 did you receive an error message?
Method 1:
I suggest you to follow the steps and check.
How to automate the defragmentation in Windows 7 (this also applies to windows vista) and the Appendix
(a) start the Task Scheduler to Accessories-> system tools.
(b) on the right pane of the most Select create basic task.
(c) enter a name for the task. The description is optional, then click on Next.
(d) in the job triggers, select the option that works for you. We go for weekly defragmentation and click on Next.
(e) choose the day and time according to your preference when you want the Defragmenter to run every week, click on Next.
(f) choose a program among the actions, click on Next.
(g) type defrag/c/v/u in the program/script text box and select Next and then OK.
the parameters h) review of the task and complete the task. Defragmentation will now load on the time and day that you have specified every week.
(i) the argument/c implies all volumes, if you want to defragment only a single or some partitions replace c/c/c with the drive you want to defrag i.e. c: d: etc.. The argument and / v and / u display out of fragmentation and advancement in the command window respectively
I also suggest that you check for disk error.
Check your hard drive for errors
http://Windows.Microsoft.com/en-us/Windows-Vista/check-your-hard-disk-for-errors
Important: When running chkdsk on the drive hard if bad sectors are found on the disk hard when chkdsk attempts to repair this area so all available data on this risk to be lost
-
I ordered a Dell 430 with 10 14 expected delivery date. Delevery scheduled tomorrow on 15 May. I was please with one day to go. Just got an email saying due to excessive demand that your date of delivery is delayed. New delivery date of June 15. What a disappointment. Can I cancel? If I was told that it would take more than six weeks to get a pc I would not order it. When they knew they were getting to order several? 1 day and then they let me know. I've been checking the status of my order and nothing then BAM. I think that there is deception here. Can I cancel my order? Certainly, he was not in production at the beginning, can they get away with this probably been lied to. I don't think I'll buy anything from this company again.
Really very disappointed.
mappyman
Post locked due to the age of the thread. If you have a similar problem, please start a new post.
-
Hi all
in another company, a few years ago I was using Oracle Workflow Manager to coordinate the processes that were responsible for feeding my data warehouse.
No, I see that it is no longer supported or developed.
Is there something different now?
There is in the case of some "no Oracle" software to implement a workflow?
My db is an Oracle 11.2.0.3 EE.
Thanks in advance,
Samuel
OBIEE and his successor Oracle Data Integrator are scheduled to carry out ETL work on datawarehouses.
Sybrand Bakker
Senior Oracle DBA
Maybe you are looking for
-
I see two windows 'readers' when I boot with the Option key
I had to reinstall Windows 10 (with BootCamp). Now, I see two windows 'readers', when I boot with the Option key button. How can I remove a?
-
I was told to update Adobe Flash Player, what I did without problem. I was also told to update Adobe Acrobat NPAPI plugin. When I click Update now, nothing happens. I'm just brought back the same screen. All of the suggestions.
-
the screen turns black with blue lettering, and I have to restart my computer to restart! What does that mean?
-
My inkjet F4488 printer does not recognize the paper. "" Although enough bunch of paper printer alwlays get a display of error message "paper" is placed on the tray. PL. help. Prema
-
Optional hardware update interfering with internet connection
I downloaded two support.microsoft.com optional hardware updates this past weekend, and one of them is interfering with my internet connection. I am running Windows XP Edition family and try to use internet explore to connect. I talked to tech supp